Delays beset DHS financial systems procurement

Contract expected in second quarter of 2010

The Homeland Security Department is more than a year behind schedule and too reliant on contractors in its second attempt to integrate its financial management systems, according to a new report from the Government Accountability Office.

The Transformation and Systems Consolidation (TASC) program was initiated in June 2007 as a successor to the eMerge2 financial systems consolidation initiative, which was canceled after two years of development. At the time, the goal of TASC was to migrate systems to an existing system in use at several DHS agencies; however, following a bid protest, DHS revised its strategy to instead acquire an integrated commercial-off-the-shelf software system to be deployed departmentwide.

Under its pre-protest timeline, DHS anticipated that several of its smaller operating agencies — including the Office of Health Affairs and the Directorate for Science and Technology — would have begun operations on the department’s integrated system by Nov. 30, 2008, the GAO said in the report dated Dec. 7.

Now, the plan is to select a vendor by the second quarter of fiscal 2010. The bid protest and litigation contributed to the delays, GAO said.

Meanwhile, two new concerns have emerged that pose “unnecessary risks” to the transformation program, according to the report. First, DHS is too reliant on the selected contractor to complete key documents for requirements management, testing, data conversion and quality assurance, GAO said.

“The extent of DHS’ reliance on contractors to define and implement key processes needed by the TASC program, without the necessary oversight mechanisms to ensure that the processes are properly defined and effectively implemented, could result in system efforts plagued with serious performance and management problems,” the GAO concluded.

In addition, DHS’ Validation and Verification contractor for the TASC procurement was not independent enough, GAO said. DHS officials have restructured the contract to address those concerns.

GAO previously reviewed progress on the transformation project in 2007 and recommended that the department define a financial management strategy, develop a concept of operations, incorporate disciplined processes and perform human capital planning. DHS has partially implemented those recommendations, GAO said.

However, DHS has not taken action on two additional recommendations: to standardize business practices across the department and to develop detailed migration and consolidation plans. DHS will not know all the information it needs until it selects a contractor, GAO said.

GAO makes seven recommendations and reaffirms its six prior recommendations for the TASC program. DHS officials agreed with the recommendations and said they had taken action to complete them, according to the report. GAO said those actions were completed for one recommendation only.

The new report expands upon concerns raised at a congressional hearing in October and by the DHS Office of Inspector General earlier this year.

About the Author

Alice Lipowicz is a staff writer covering government 2.0, homeland security and other IT policies for Federal Computer Week.

Reader Comments

Tue, Dec 8, 2009 Another Concerned Taxpayer

This massive program needs to be delayed or put on hold until all this is worked out. Check out the Congressional testimony - they don't even know what it will cost - the delta between estimates is over $500M. Give me a break. Congress - hold them up on this before they waste $450M - $1B of taxpayer money.

Please post your comments here. Comments are moderated, so they may not appear immediately after submitting. We will not post comments that we consider abusive or off-topic.

Please type the letters/numbers you see above

What is your e-mail address?

My e-mail address is:

Do you have a password?

Forgot your password? Click here
close

Trending

  • Dive into our Contract Award database

    In an exclusive for WT Insider members, we are collecting all of the contract awards we cover into a database that you can sort by contractor, agency, value and other parameters. You can also download it into a spreadsheet. Our databases track awards back to 2013. Read More

  • Navigating the trends and issues of 2016 Nick Wakeman

    In our latest WT Insider Report, we pull together our best advice, insights and reporting on the trends and issues that will shape the market in 2016 and beyond. Read More

contracts DB

Washington Technology Daily

Sign up for our newsletter.

I agree to this site's Privacy Policy.